Our pilots

From plans to plants

​

ResNRJwater is about turning water infrastructure into an active part of the energy system. Wastewater treatment plants use a lot of energy. But they also have space, steady demand and existing grid connections. That makes them ideal places to produce, store and manage renewable energy.


The pilots are where this idea is put to the test. After two years of planning and preparation, the first pilot installations are now being built in Belgium, Germany and France. On this page, we follow their progress, from construction to operation and first results.


ResNRJwater will support municipalities and waterboards to take up resilient renewable energy source (RES)-based solutions in urban and rural regions of Northwest Europe. Innovative solutions will be piloted on infrastructure of the water and waste water sector to maximise the exploitation of RES:


  • Different technology types to facilitate the uptake of RES: discontinuous solar and small-wind power, continuous green gas
  • A smart energy management and storage system for a decentralised and resilient energy supply based on RES
  • A concept for consumption of energy-surplus or derivates produced from RES at the water and waste water sector


Pilot sites

#1 Aquafin, Belgium 

Battery energy storage in Merksem

 

Status: Built 


At the Merksem wastewater treatment plant, three stormwater pumps protect the surrounding area from flooding during heavy rainfall. To keep them running during a power cut, Aquafin needed an emergency power supply. For the first time, it chose a battery energy storage system (BESS) instead of a diesel generator. When heavy rain is forecast, a smart control system keeps enough capacity in reserve for the pumps. The rest of the time, the battery trades on the electricity market and helps keep the grid stable. The BESS in Merksem is the first of seven ResNRJwater pilots to be built.

Fact sheet for the BESS in Merksem

Soon you will be able to download a detailed factsheet with a concrete solution for a concrete problem, the technical drawing and further contact information of the BESS of AQUAFIN in Merksem, BE


LIPPEVERBAND, Germany – Battery energy storage in Dorsten 

Status: to be Built



Fact sheet for the BESS in Dorsten

Download a detailed factsheet with a concrete solution for a concrete problem, the technical drawing and further contact information of the BESS of LIPPEVERBAND in Dorsten, DE

​​